A change order is a short written amendment to a job you already agreed to. It records what changed, what it costs, how it affects the schedule, and that both sides agreed before the work was done.
When you need one
- The client asks for added, removed, or upgraded work.
- You uncover a site condition nobody could see at estimate time, such as rot, old wiring, or a failed drain line.
- An inspector or building code requires work that was not in the original scope.
- A specified product is unavailable and the substitute changes the price or timing.
What to include
- Your business details, the client, and the job site address.
- A change order number and date, plus a reference to the original estimate or contract.
- A plain description of the change and the reason for it.
- Itemized additions and credits, with taxes where they apply.
- The schedule impact, even when the answer is “no impact to completion date”.
- Signature and date lines for both the contractor and the client.
Show the contract math
Disputes usually come from confusion about the new total. Print four figures together so there is nothing to work out.
| Line | Example |
|---|---|
| Original Contract Sum | $6,400.00 |
| Previously Approved Change Orders | +$1,200.00 |
| This Change Order Net Change | -$300.00 |
| Revised Contract Total | $7,300.00 |
Get it signed before the work starts
A signed change order is far easier to bill than a verbal yes. Send it as a PDF, collect the signature and date, and only then order materials or start the extra work. Count only approved change orders toward the revised total and the final invoice.
Contract and lien rules differ by state and province, and some require written change orders for residential work. Check the rules where you work, or ask a construction attorney, if a job is large or disputed.